REC Silicon: Part 5

Emergency Vent System Tank Replacement

Project Details

The Silane Plant 3 Emergency Vent System Scrubber Tank has reached its end of service life and is being replaced. The replacement tank is a 32 Ft diameter by 40 Ft high FRP tank matching its predecessor. The tank will be field assembled within the confines of the existing structure.

Key Project Challenges

  • Replace an existing tank surrounded by a heavy industrial structure currently supporting vital processes.
  • Aggressive schedules to complete preparatory field work prior to receipt of the new tank.
  • Select mechanical equipment was upgraded in addition to the tank
  • Sequencing to support a phased demolition and rebuild effort.
  • A tight labor market presented challenges securing experienced contractors and labor

IPC Solutions

  • IPC, REC, and the tank supplier developed an installation sequence allowing the existing structure to remain substantially in place, saving considerable time and expense by retaining the structure.
  • Developed Scopes of Work defining clear boundary limits for each trade contractor. Secured contracts with REC for that work.
  • Close coordination of contractor manpower and materials to ensure sufficient resources to make progress. Management of change orders.
  • Contracts were Multiple Prime Contracts direct to REC Silicon

Owner’s Benefit

  • Considerable savings of time and funding were achieved by retaining the existing structure, which greatly shortened the overall schedule.
  • Process reliability was improved due to upgraded mechanical equipment.
  • Lessons learned on this project can be replicated at Plant 4 should that tank require replacement as well.
  • Successful project execution resulted in improved relationships between REC and local contractors for future projects.

Leave a Comment